October 13th 2026, 10:49 PM
Oracle Urges FERC to Fast-Track New Mexico Gas Pipeline for AI Data Center
Key Summary
Oracle is seeking FERC to expedite the Green Chile pipeline project, which will supply fuel to Oracle's Project Jupiter data center in New Mexico. The project aims to create 5,800 peak construction jobs and generate $1.1 billion in annual county output, but has been delayed due to route issues and environmental concerns. Oracle is considering a trucking workaround, which could be more expensive, to ensure the project's timeline.
Please see our real time news feed on our Home Page
What Oracle is asking for
The appeal came from Josh Pitcock, Oracle's senior vice president of government affairs. He made it in a letter dated October 13, 2026. Pitcock's argument centers on time. Oracle says continued delays threaten the project's schedule, its potential job creation and the wider economic benefits it expects to bring to the region.How the pipeline got stuck
The original schedule called for the pipeline to enter service on August 15, 2026. The new projected date is February 1, 2027. The slip traces back to the route. The first proposed path crossed state trust lands, and the New Mexico State Land Office rejected it twice.The trucking workaround
Oracle is not betting everything on FERC's calendar. The company is weighing an interim plan to truck in compressed natural gas so operations can begin before the pipeline is ready. The approach has precedent inside Oracle. It has already been used at smaller facilities in Utah and Texas.The economic pitch
Oracle estimates the project will generate nearly 5,800 peak construction jobs. Projections put annual output for Doña Ana County at up to $1.1 billion during the buildout phase. Oracle has also pointed to a potential economic impact exceeding $13 billion over the life of Project Jupiter.What this means
The project illustrates a shift in how tech companies source power. Rather than waiting on the regional grid, Oracle plans to generate electricity on site with fuel cells. That sidesteps grid bottlenecks but swaps them for fuel supply bottlenecks, and this pipeline is the proof. For New Mexico, the state has already turned down the trust land route twice and lost fees in the process, yet it also stands to gain thousands of construction jobs and substantial county output if the project proceeds.#Oracle#US#FERC#NewMexico#AIdatacenter